DP Electric was contracted to complete CyrusOne building one, two, three, four and eight. Each of these buildings ranged from core and shell to completing full interiors which were 7.5MW builds. From ground up to commissioning, building four took a record setting 107 days.
Location
Chandler AZ
Owner
Confidential
General Contractor
DPR Construction
Size (sf)
4,200,000