Thew Elementary School

Tempe, Arizona

Project Description
Thew Elementary School was a fast paced installation of a combination roof mount and carport/shade structure PV system that required work to be performed during off-hours at night to minimize any impact on the daily function/routine of the school. The project presented additional challenges due to city ordinances with noise restrictions that went into effect at 10pm each evening, & further compression of the schedule on the back end of the project due to delays with the underground scope & raceway installation that was subcontracted by SolarCity.

Size:  249 KW
Owner: 
Tempe School District
Contractor:
 SolarCity
Completion: 
December 2012